EPA Issues Proposed Morris Run Well Order

Washington PA Observer Reporter
6 August 2010
By Bob Niedbala, Staff writer
niedbala@observer-reporter.com

The U.S. Environmental Protection Agency has proposed a final administrative order for the CNX Gas Co.'s Morris Run injection well in Wayne Township that will include the plugging of the well.

EPA issued notice of the proposed order Wednesday for alleged violations in the operation of the well originally cited in a proposed order issued last August.

Both orders call for the company to pay a $157,500 penalty for allegedly failing to adequately staff and secure the well site, monitor the well's cumulative volume and report noncompliance with its permit. The final order also calls for the company to plug the well within 60 days of its effective date.

A comment period on the proposed order runs until Sept. 20, and if no significant issues are raised, the final order should be signed shortly afterward, said Karen Johnson, chief of groundwater and enforcement for EPA's Region 3.

CNX received a permit for the injection well at the Morris Run Mine Shaft of Consol Energy's closed Blacksville No. 1 Mine in 2005 for disposal of waste water, or brine, from the company's coal bed methane wells.

The company was permitted to dispose up to 150,000 barrels of coal bed methane waste water a month in the well, a mine pool more than 700 feet below surface.

The well site was to be locked and the tanker truck tap-in to the well contained in a locked valve box. The permit also required the site be adequately staffed and the cumulative volume of the waste water continuously monitored.

According to the proposed order:

* Between Dec. 23, 2006, and Aug. 20, 2008, no flow meter was operational at the well to measure cumulative volume. During an inspection Aug. 7, 2008, EPA found the gate open, no lock on the valves at the truck offloading area and no flow meter in use. The wire from the previous flow meter had been cut and no CNX staff or operator was present at the site, EPA said.

* Between Dec. 23, 2006, and Aug. 20, 2008, the only method of recording the volume of fluid discharged at the well was a truck log book kept at the site. Since Sept. 1, 2005, not all truck drivers that discharged at the site recorded or accurately recorded their discharge in the log book.

* Company records of sampling results of fluids deposited into well indicate that between about September 2007 and March 2009 at least 100 truckloads of fluid were disposed of at the site with total dissolved solid (TDS) levels that "varied significantly" from expected TDS levels provided in the permit application and eight truckloads of water contained E coli bacteria, indicating sewage.

The permit allowed the company to dispose of water containing up to 25,000 milligrams per liter TDS. The order also notes CNX used contract haulers to transport water to the well and some of those hauler also hauled septic waste.

The injection well became an issue following the fish kill in Dunkard Creek last September. Questions were raised about what might have been dumped into the well and whether that water might have migrated underground into the nearby Blacksville No. 2 Mine.

Investigators determined a toxic bloom of golden algae led to the fish kill. They also said high levels of TDS originating from the Blacksville No. 2 mine discharge created conditions for the algae bloom.

EPA, however, doesn't believe there was any connection between the injection well and fish kill, Johnson said. Chemical characteristics of the waste water disposed of in the well was different from that found in the creek, she said.

Tests of water in the well before injection began and after it ended also showed little change in the water's chemical makeup, she said. The estimated amount of waste water injected into the well, in addition, was very small in relation to the volume of water in the mine pool.

Joe Cerenzia, CNX spokesman, said the company corrected problems at the well when it learned of them in 2008 and later voluntarily ceased disposed of waste water there.

The company also made the decision to plug the well, he said. The execution of the final order, Cerenzia said, should bring the matter to a close.